What does an EOT claim consultant do on a Saudi project?
We turn a delay into an entitlement that can be tested, or test one that has been claimed against you. On every matter we work through the same chain:
- Confirm the governing law and contract. The tender date decides which procurement law applies, and the particular conditions decide the notice and programme rules.
- Collect the record. Programmes and updates, notices, correspondence, minutes, progress reports and site records, with a note of what each can prove.
- Test the programme. The Primavera P6 baseline and updates are checked for logic, constraints and reported progress before any delay is measured.
- Measure the delay. Using a method the records can sustain, separating employer-risk events from contractor-risk causes period by period.
- Set out the entitlement. An extension request, a claim or a response that the employer, a court or a tribunal can follow step by step.
When can a Saudi government contract be extended?
Article 72 of the Government Tenders and Procurement Law sets five grounds on which the contract period is extended and the delay penalty waived: additional work, insufficient annual funding, delay caused by the government entity or by emergency circumstances, delay for reasons beyond the contractor's control, and a suspension order by the entity for reasons not attributable to the contractor. These grounds are unchanged under the new law. Each has to be proved from the record, so contemporaneous evidence linking delay to owner actions, funding shortfalls, suspensions or events beyond the contractor's control decides the outcome.
The new law was approved by Royal Decree No. M/76 dated 27/2/1448H (10 August 2026) and published in the Umm Al-Qura Official Gazette on 4 September 2026. Under Article 101 it takes effect 120 days after publication, which by simple count is 2 January 2027, although the Ministry of Finance has not yet confirmed the start date. Article 70 caps delay penalties on works at 15% of contract value, down from 20% under the 2019 law, unless the Minister approves a higher cap and bidders are told before they bid. A lower cap reduces exposure, not the burden of proving cause. Works tendered under the 2019 law stay under it, and exemptions granted under it continue, including those for the Public Investment Fund, so we confirm the position with your counsel first. See what the new procurement law changes.
How do giga-project contracts handle extension of time?
Most giga-project employers use FIDIC-based forms with heavy amendment, and some use bespoke or NEC-based terms, so programme submission periods, review times, software, reporting formats and notice provisions must be read from the particular conditions and the employer's requirements. Where the unamended FIDIC clauses apply, the 1999 Red Book requires notice within 28 days of awareness and a fully detailed claim within 42 days under Sub-Clause 20.1, and the 2017 Red Book requires a Notice of Claim within 28 days and a fully detailed Claim within 84 days under Sub-Clauses 20.2.1 and 20.2.4. Under NEC4, the contractor notifies a compensation event within eight weeks of becoming aware under clause 61.3, with stated exceptions. On giga-projects, supply chains stretch and delay exposure compounds quickly, so we run delay analysis as a live discipline rather than a reconstruction at final account.
How does the Civil Transactions Law affect delay claims?
Since 16 December 2023, the Civil Transactions Law (Royal Decree M/191) has codified agreed compensation and the construction contract (muqawala). It includes provisions that can rebalance responsibility where more than one party contributed to harm, so the delay analysis has to separate causes clearly, because a tribunal may look at each party's share rather than an all-or-nothing result. A court may also, on the contractor's application, reduce agreed delay compensation that was overestimated or where the obligation was partly performed. Your counsel advises on the law; we keep our evidence to programme, records and causation.
Where are Saudi delay disputes decided?
Disputes with government authorities are generally heard by the Board of Grievances. Under the new procurement law, compensation claims for owner breach go to the competent court, bid grievances and price-adjustment requests go to a Ministry of Finance committee, and arbitration, including at the SCCA, needs the Minister's approval under Article 94. Private-sector construction disputes are often arbitrated at the Saudi Center for Commercial Arbitration, and SCCA arbitrations filed since 1 May 2023 run under its 2023 Rules.
Clients appoint us in one of two roles, never combined on the same matter: as party-appointed support, building and testing the delay evidence with you and your counsel, or as an independent expert whose duty is to the court or tribunal. We never act as mediator or arbitrator. See our dispute avoidance and resolution support.
Which delay analysis method suits a Saudi claim?
The one the records can sustain, explained in the report, because a tribunal will test the choice. Contemporaneous time impact analysis needs a well-maintained programme and a datable event. Windows and time-slice analysis needs contemporaneous updates with logic maintained through the delay period. Planned against actual comparison suits projects where the updates are unreliable but the as-built record is sound. Our Delay Method Selector and the guide to time impact analysis vs windows analysis explain the choice, and when to bring in an EOT claim consultant explains why the first weeks matter.
Our references
Our forensic reference is Hafeet Rail, a rail programme in Oman in significant dispute, where our forensic windows analysis separated design-change impacts from concurrent contractor causes and set out a substantiated EOT entitlement. On Etihad Rail Stage 2 and 3 in the UAE we provided independent systems assurance across construction and commissioning. Read more about Project Assure in Saudi Arabia and our forensic planning and delay analysis service.