Choosing a delay analysis method: the six techniques and when each holds
A practical guide to the six SCL delay analysis methods: what records each needs, prospective vs retrospective, and which forum favours which.
ReadMethod selection is governed by two things: what the contract requires, and what the contemporaneous record can actually sustain. An analysis whose method the records cannot support will be discounted however sound the underlying entitlement.
Choosing a forensic delay analysis method is a judgement about evidence, not preference. It turns on whether a credible baseline exists, what the contract requires, what state the contemporaneous updates are in, and whether concurrent causes have to be separated. More than one method is often defensible on the same facts, and a report that runs a primary method and a cross-check is usually stronger than one that runs either alone.
What are you trying to prove?
Delay methods answer a different question from disruption or acceleration. This decides whether the selector applies at all.
Is there a credible baseline programme?
Every technique here depends on one. Answer this honestly before anything else.
When is the assessment being made?
Prospective methods model an event as it arises. Retrospective methods measure what the record shows.
What does the contract require?
Asked whichever way you answered the last question, because a prescribed method still binds you after the event.
What state are the contemporaneous records in?
Answer against the weakest part of the delay period, not the best of it. If more than one statement describes your project, pick that one; the selector will offer the other as a cross-check rather than discarding it.
Do employer-risk and contractor-risk events affect the same period of critical delay?
Concurrency drives method choice, because only some methods separate causes period by period.
General guidance, not advice, and no client relationship is created by using it. Method selection is fact-specific and contract-specific. More than one method may be defensible on the same facts, and the appropriate choice should be made by a qualified analyst on the actual records and the governing contract and law. Entitlement consequences, particularly for concurrent delay, are determined by the contract and the applicable law and differ between jurisdictions.
This selector is Project Assure's own synthesis. It is not endorsed by, affiliated with, or derived from the text of the Society of Construction Law or AACE International. Method names are terms of art in general use.
Method names and the prospective/retrospective distinction follow the Society of Construction Law Delay and Disruption Protocol, 2nd edition (February 2017). The Protocol identifies six techniques; a straightforward as-planned versus as-built comparison is widely used in practice alongside them and is included here, making seven.
| Method | Viewpoint | What it does | What your records must sustain | Where it is weak |
|---|---|---|---|---|
| Time Impact Analysis | Prospective | A fragnet modelling the delay event is inserted into the programme in force at the time, and the predicted effect on completion is read off. | A well-maintained programme in force at the time of the event, and an event that can be discretely identified and dated. | Data-hungry and sensitive to update quality. It produces a forecast, and a tribunal reviewing a completed project may prefer what actually happened. |
| Impacted As-Planned | Prospective | Delay events are added into the baseline programme to model their theoretical effect. | A sound, logic-linked baseline. | It relies entirely on a sound baseline and ignores what actually happened on site. A tribunal reviewing a completed project can see the as-built, so a model that ignores it reads as academic. |
| Time Slice Windows | Retrospective | The programme is divided into periods; critical-path movement is measured in each window against the updated schedules, and the delay in each window is then attributed to causes from the contemporaneous record. | Contemporaneous programme updates with logic maintained through the delay period. | It can only separate employer and contractor causation if the contemporaneous updates actually captured both, with logic, fragnets and notices that match the events. |
| As-Planned versus As-Built Windows | Retrospective | A windows analysis driven by factual records rather than programme logic, comparing intended against actual progress period by period. | Reliable period-by-period progress and as-built data. | Causation is inferred from the factual record rather than modelled through logic, so it is more contestable where causes overlap. |
| Retrospective Longest Path Analysis | Retrospective | The as-built longest path is traced back from actual completion to identify what in fact drove the finish date. | A reliable, detailed as-built with dated actuals. | It identifies the driving path rather than the cause. It applies no contemporaneous test of criticality, and it is weak on separating employer and contractor responsibility. |
| Collapsed As-Built (but-for) | Retrospective | Delay events are stripped out of the as-built programme to show what would have happened without them. | A complete as-built programme whose logic was recorded contemporaneously. | It requires a fully logic-linked as-built, which is rare and often reconstructed after the fact. It reasons from effect back to cause, applies no contemporaneous criticality test, and the result is sensitive to the order in which events are removed. |
| As-Planned versus As-Built | Retrospective | A visual, factual comparison of the intended programme against what actually happened. | A baseline and an as-built record, both good enough to compare. | It shows correlation, not causation, and is weak where multiple causes overlap. |
Delay Analysis Method Selector v2.0 · Published 27 July 2026 · Review due July 2027 · Aligned to SCL Delay and Disruption Protocol, 2nd edition (February 2017) · © 2026 Project Assure Private Limited · Free to reproduce and share with attribution to projectassure.in
A practical guide to the six SCL delay analysis methods: what records each needs, prospective vs retrospective, and which forum favours which.
ReadWhen Time Impact Analysis is the right delay method, when windows or as-planned vs as-built analysis wins, and what the SCL Protocol expects.
ReadA concurrency argument is decided by records made years before the tribunal. Here is the month-three discipline that decides month-thirty disputes.
Read
Our forensic planning team can test your position before you commit. A principal replies within one working day.