Saudi Arabia's new procurement law · what changes for programmes, controls and claims
What Saudi Arabia's 2026 Government Tenders and Procurement Law changes on government construction contracts: variations, delay penalties, transition, claims.
ReadDelay and extension of time, claims, schedule quality, risk and assurance, written by the people who do the work in India and the GCC.
What Saudi Arabia's 2026 Government Tenders and Procurement Law changes on government construction contracts: variations, delay penalties, transition, claims.
ReadA decision guide for owners and contractors in the UAE and GCC: the signals it's time to engage an independent extension-of-time and delay consultant.
ReadAn independent Primavera P6 schedule audit surfaces broken logic, false float and critical-path manipulation before they cost you at tribunal.
ReadA practical guide to the six SCL delay analysis methods: what records each needs, prospective vs retrospective, and which forum favours which.
ReadHow prolongation and disruption quantum is actually proved under FIDIC, records, methods and the delay foundation that makes a claim defensible.
ReadIndependent project assurance verifies whether a project's own reporting still tells the truth. What it covers, and when owners, lenders and boards need it.
ReadStress-test your tender programme before you sign. Independent bid schedule review that exposes optimism, lead-time and FIDIC risk before it becomes a dispute.
ReadThe 14 DCMA schedule checks and their thresholds, BEI and CPLI explained, how to run the assessment in Primavera P6, and a worked failing example.
ReadP50 is a 50% chance of finishing by the date, P80 an 80% chance. Which to plan to, which to commit to, and how the gap sizes schedule contingency, with an example.
ReadA concurrency argument is decided by records made years before the tribunal. Here is the month-three discipline that decides month-thirty disputes.
ReadNEC4 and FIDIC both lead to an extension of time, but notice regimes, time-bars and assessment differ in ways that decide entitlement.
ReadWhen Time Impact Analysis is the right delay method, when windows or as-planned vs as-built analysis wins, and what the SCL Protocol expects.
ReadHow NEC4 compensation events work: early warning, the eight-week notification bar and why prospective assessment rewards real-time management.
ReadOn multi-contract rail programmes a package can be complete on paper while the work it enables is not ready. Stage-gate assurance closes the gap.
ReadOpen ends, hard constraints, negative float, no baseline: seven structural red flags that a Primavera P6 schedule has stopped modelling the work.
ReadThe Delay Method Selector, an EOT claim readiness checklist and a DCMA 14-point schedule checklist, free to use and share.
Browse resources