Dependency-aware risk management: pricing what the register cannot see
A risk register scores each risk alone. Five steps to set correlation coefficients between risks, price the gap at P50, P80 and P90, and target mitigation.
ReadDelay and extension of time, claims, schedule quality, risk and assurance, written by the people who do the work in India and the GCC.
A risk register scores each risk alone. Five steps to set correlation coefficients between risks, price the gap at P50, P80 and P90, and target mitigation.
ReadWhat Saudi Arabia's 2026 Government Tenders and Procurement Law changes on government construction contracts: variations, delay penalties, transition, claims.
ReadA decision guide for owners and contractors in the UAE and GCC: the signals it's time to engage an independent extension-of-time and delay consultant.
ReadData centre commissioning runs in five levels, from factory witness tests (L1) to integrated systems testing (L5). What each proves and how to programme it.
ReadHow to control a data-centre programme in India, the UAE, Saudi Arabia and Oman: the power date, long-lead equipment, L1 to L5 commissioning and delay damages.
ReadAn independent Primavera P6 schedule audit surfaces broken logic, false float and critical-path manipulation before they cost you at tribunal.
ReadA practical guide to the six SCL delay analysis methods: what records each needs, prospective vs retrospective, and which forum favours which.
ReadHow prolongation and disruption quantum is actually proved under FIDIC, records, methods and the delay foundation that makes a claim defensible.
ReadIndependent project assurance verifies whether a project's own reporting still tells the truth. What it covers, and when owners, lenders and boards need it.
ReadStress-test your tender programme before you sign. Independent bid schedule review that exposes optimism, lead-time and FIDIC risk before it becomes a dispute.
ReadThe 14 DCMA schedule checks and their thresholds, BEI and CPLI explained, how to run the assessment in Primavera P6, and a worked failing example.
ReadP50 is a 50% chance of finishing by the date, P80 80%, P90 90%. Which to plan to, which to commit to, how to set contingency and compare forecasts.
ReadA concurrency argument is decided by records made years before the tribunal. Here is the month-three discipline that decides month-thirty disputes.
ReadNEC4 and FIDIC both lead to an extension of time, but notice regimes, time-bars and assessment differ in ways that decide entitlement.
ReadWhen Time Impact Analysis is the right delay method, when windows or as-planned vs as-built analysis wins, and what the SCL Protocol expects.
ReadHow NEC4 compensation events work: early warning, the eight-week notification bar and why prospective assessment rewards real-time management.
ReadOn multi-contract rail programmes a package can be complete on paper while the work it enables is not ready. Stage-gate assurance closes the gap.
ReadOpen ends, hard constraints, negative float, no baseline: seven structural red flags that a Primavera P6 schedule has stopped modelling the work.
ReadA Primavera P6 schedule review checklist: data date, calendars, logic, constraints, float, critical path, resources, DCMA thresholds and a sign-off table.
ReadThe data date in P6 is the cut-off between actual progress and forecast. How it drives forecasts, float and EVM, data date vs status date, and common mistakes.
ReadHow to resource load a Primavera P6 schedule: resource types, duration types, cost loading, EVM and S-curves, levelling, and the six mistakes that fail review.
ReadNegative float means an activity's late finish is earlier than its early finish. How P6 calculates total and free float, what causes negative float, and fixes.
ReadHow each Primavera P6 constraint works, hard vs soft constraints, what Mandatory Start does, why DCMA caps hard constraints at 5%, and how to audit them.
ReadOut-of-sequence progress in Primavera P6: what it is, why it happens, how it distorts float and the critical path, and five steps to find and fix it.
ReadRetained logic vs progress override vs actual dates in Primavera P6: how each schedules out-of-sequence work, and why the choice matters in a delay claim.
ReadHow to set a baseline in Primavera P6, assign it, read baseline variance, avoid the mistakes that zero it out, and keep a basis of schedule document.
ReadOpen ends in Primavera P6: what missing logic and dangling activities are, the DCMA 5% threshold, how to find them in P6 and how to fix them with logic.
ReadPrimavera P6 calendars explained: global vs project vs resource calendars, which one sets an activity's dates, and how calendars affect durations and float.
ReadHow to read a Primavera P6 XER file without P6: the %T, %F and %R format, the PROJECT, TASK and TASKPRED tables, and what to check first in any XER.
ReadWhat an as-built schedule is, where the data comes from, how to rebuild one from P6 updates, find the as-built critical path and use it in delay analysis.
ReadHow to read an S-curve in a construction schedule: planned vs earned vs actual curves, what the shape shows, building one from P6, and common pitfalls.
ReadWhat a work breakdown structure is, the 100% rule, how to build a WBS in Primavera P6 and Excel, WBS vs activity codes, and the common mistakes to avoid.
ReadHow to build a 3-week lookahead schedule from Primavera P6: the filter, a template, make-ready constraint checks from Last Planner, and mistakes to avoid.
ReadHow to write a schedule basis memo (basis of schedule): what to include, common omissions, how it differs from a schedule narrative, and a 14-item checklist.
ReadPrimavera P6 vs Microsoft Project for construction: a neutral comparison of database, calendars, baselines, EVM and file formats, and when to use each tool.
ReadDCMA runs 14 numerical checks on the schedule file. GAO sets 10 best practices in four characteristics. How they overlap and differ, and when to use each.
ReadEarned value management in construction: PV, EV and AC, SPI and CPI formulas, EAC forecasting, a worked example and why SPI misleads near completion.
ReadCrashing adds resources, fast-tracking overlaps work. How each compresses the critical path, cost slope, risks, and when acceleration becomes a claim.
ReadThe Delay Method Selector, an EOT claim readiness checklist and a DCMA 14-point schedule checklist, free to use and share.
Browse resources