Project Assure
Home / Insights
Insights

Insight from live mandates

Practitioner writing on schedule forensics, quantitative risk, delay and EOT entitlement, and project controls, the disciplines behind every Project Assure engagement.

Claims & Entitlement · 4 min read

When to bring in an EOT claim consultant · and why timing decides it

A decision guide for owners and contractors in the UAE and GCC: the signals it's time to engage an independent extension-of-time and delay consultant.

Read →
Schedule Forensics · 4 min read

What an independent Primavera P6 schedule audit actually finds

An independent Primavera P6 schedule audit surfaces broken logic, false float and critical-path manipulation before they cost you at tribunal. Here is what it finds.

Read →
Schedule Forensics · 4 min read

Choosing a delay analysis method: the six techniques and when each holds

A practical guide to the six SCL delay analysis methods: what records each needs, prospective vs retrospective, and which forum favours which.

Read →
Contracts · 4 min read

FIDIC claims: how prolongation and disruption quantum is actually proved

How prolongation and disruption quantum is actually proved under FIDIC, records, methods and the delay foundation that makes a claim defensible.

Read →
Assurance · 4 min read

Independent project assurance: what it is, and when owners and lenders need it

Independent project assurance verifies whether a project's own reporting still tells the truth. What it covers, and when owners, lenders and boards need it.

Read →
Risk Discipline · 4 min read

Bid and tender programme assurance: stress-testing a schedule before you sign

Stress-test your tender programme before you sign. Independent bid schedule review that exposes optimism, lead-time and FIDIC risk before it becomes a dispute.

Read →
Schedule Forensics · 7 min read

DCMA 14-Point Assessment explained · with a worked P6 example

What the DCMA 14-point schedule assessment actually checks, why BEI and CPLI matter, and a worked Primavera P6 example, plus how to run all 14 checks in under a minute.

Read →
Risk Discipline · 6 min read

P50 vs P80: how to set a defensible completion date

A single completion date is a fiction. Here is how quantitative schedule risk analysis (QSRA) turns P50, P80 and P90 into decisions about the working programme, contractual commitment and contingency.

Read →
Claims & Entitlement · 7 min read

Concurrent delay: the argument you win in month three, not month thirty

By the time a concurrency argument reaches a tribunal, the outcome is largely determined by records created years earlier. Here is the month-three discipline that decides month-thirty disputes.

Read →
Contracts · 8 min read

NEC4 vs FIDIC EOT claims: what actually differs

Both NEC4 and FIDIC give a route to an extension of time, but their notice regimes, time-bars and assessment philosophy differ in ways that decide entitlement. A practical comparison.

Read →
Schedule Forensics · 6 min read

Time Impact Analysis vs windows analysis: choosing the right delay method

Prospective vs retrospective delay analysis: when Time Impact Analysis (TIA) is the right method, when a windows / as-planned vs as-built analysis wins, and what the SCL Protocol expects of each.

Read →
Contracts · 6 min read

NEC4 compensation events: the early-warning discipline that protects entitlement

How NEC4 compensation events actually work: the early-warning register, the eight-week notification bar, and why prospective, quotation-based assessment rewards contractors who manage in real time.

Read →
Engineering Assurance · 7 min read

Systems assurance on rail: linking design maturity to construction readiness

On multi-contract rail programmes, a package can be 'complete' on paper while the work it enables is not ready. Independent systems assurance and design stage-gates close that gap.

Read →
Schedule Forensics · 6 min read

Seven red flags in a Primavera P6 schedule · and what they cost you

Open ends, hard constraints, negative float, missing baseline: seven structural red flags that tell you a Primavera P6 schedule has stopped being a model of the work. And how to catch them in seconds.

Read →