What does a project controls consultant do on a Saudi project?
We make the monthly numbers trustworthy. For clients in the Kingdom that covers:
- Controls set-up: procedures, coding structures, roles and reporting calendars agreed before mobilisation, scaled to the contract and the owner's governance.
- Cost-loaded schedules: work and cost breakdown structures mapped to control accounts, so each Primavera P6 activity carries a budget and a measurable scope.
- Rules of credit and measurement agreed before progress is claimed, so per cent complete is evidence rather than opinion.
- Monthly performance reports showing planned value, earned value and actual cost, with SPI and CPI, written for boards, funders and site teams.
- EAC and forecast reviews that test estimates at completion and forecast dates against performance trends.
- Controls audits of an existing system: baseline integrity, schedule quality, progress rules, change control and reporting accuracy.
See our project controls and EVM service for the full scope.
How does the new procurement law change project controls?
It changes the change register most of all. The 2019 law capped change orders at a 10% increase in contract value. Under Article 67 of the new law an owner may add new items worth up to 10% of the contract value with the contractor's consent and increase existing items by up to 20%, with consent needed above 10%, but the total increase may not exceed 20% of the contract value. That means two running totals in the change register, reported monthly, so budgets, baselines and estimates at completion show the headroom left under each limit.
Packages tendered under the 2019 law keep, as a rule, its single 10% limit on increases under Article 69, so a portfolio may run both rules side by side. The new law was published in the Umm Al-Qura Official Gazette on 4 September 2026 and under Article 101 takes effect 120 days later, by simple count 2 January 2027, although the Ministry of Finance has not yet confirmed the start date. Exemptions granted under the 2019 law continue, including those for the Public Investment Fund, so we confirm with your counsel which law governs each package before building the register. See what the new procurement law changes.
What do FIDIC-based contracts in Saudi Arabia require of the programme?
Most giga-project employers use FIDIC-based forms with heavy amendment, and some use bespoke or NEC-based terms, so programme submission periods, review times, software, reporting formats and notice provisions must be read from the particular conditions and the employer's requirements. Where the FIDIC Red Book clauses apply, Sub-Clause 8.3 requires a programme, and the monthly progress report (Sub-Clause 4.21 in the 1999 edition, 4.20 in 2017) compares actual with planned progress and supports each interim payment application. We build the earned value baseline from that contract programme, so the controls report and the contractual record say the same thing.
How is earned value measured objectively?
From physical progress against agreed rules of credit and measured quantities, drawn from contemporaneous site records. Quantities are measured to the method the contract names, such as NRM2 or CESMM4, or the RICS Principles of Measurement (International), still referenced in some older contracts in the region. We compare earned value with planned value and actual cost, trace each variance back to the activities and causes behind it, and project the estimate at completion and the completion date from current performance. Our work follows EIA-748-E, ISO 21508:2018, ANSI/PMI 19-006-2019 and AACE RP 82R-13.
Why is cost and progress reporting read so closely in the Kingdom?
Because more parties now rely on it. The Expenditure Efficiency and Government Projects Authority (EXPRO), set up in 2021 and absorbing the former Mashroat programme, works with government entities on capital spending efficiency and project quality, and under the new procurement law it reviews an entity's feasibility study, estimated cost and tender documents before tendering. That review period belongs in the procurement logic of the baseline programme. The Civil Transactions Law, in force since 16 December 2023, also sets statutory rules for construction contracts (muqawala), including variations and price adjustment.
Price adjustment on government contracts is still limited to the three Article 66 triggers, so material price, tax and unforeseeable physical risks should be priced and registered explicitly, and the estimate at completion should be tested against a risk-adjusted programme. See our risk management and QSRA service and P50 vs P80.
Our references
For the World Bank climate-hazard programme on the Tawi River in India we rebuilt the baseline to realistic lead times and produced a risk-adjusted P50/P80 programme for funder-grade reporting. On Etihad Rail Stage 2 and 3 in the UAE we provided independent systems assurance across construction and commissioning. When delay has already happened, see our EOT claim consultant page for Saudi Arabia, and read more about Project Assure in Saudi Arabia.