What does a data centre consultant do?
A data centre consultant plans and controls delivery of the facility, from pre-construction to handover. At Project Assure that means building the integrated master programme, tying long-lead equipment and MEP installation to commissioning, reporting progress and earned value, and reviewing the programme's logic and risk independently. We do not design the facility. We make sure the programme to deliver it is credible.
What are the L1 to L5 commissioning levels?
They are five stages of testing commonly used on data-centre projects. L1 covers factory witness tests, L2 installation checks on site, L3 pre-functional start-up of individual equipment, L4 functional performance of complete systems, and L5 integrated systems testing of the whole facility under simulated load and failure. Definitions vary by specification, so we fix them in the programme at the outset.
Why do long-lead items drive data centre programmes?
Because generators, UPS systems, switchgear and chillers depend on factory slots that can outlast the building works. If design freeze, orders, factory witness tests and shipping are missing from the programme logic, the true critical path stays hidden until equipment arrives late. We link each item from specification to energisation, so the effect of any slip on handover is visible early.
What is the Project Assure Data Centre Intelligence platform?
It is an open-access globe of global data-centre capacity, covering 13,715 data-centre sites across 135 countries. Choose a data-centre type, such as hyperscale, colocation, edge, AI/HPC or enterprise, and a geography, and it scores market risk against peer markets, and shows the evidence and provenance behind each rating. No sign-in is needed. We use it to frame siting and phasing discussions early.
Can you review a contractor's data centre programme?
Yes. We review logic, critical path, float, resource loading and the treatment of MEP and commissioning, and run DCMA 14-point and schedule risk checks. The review tells the owner or lender whether the ready-for-service date is achievable, which interfaces threaten it, and what evidence the contractor should produce next. It can be a one-off review or a monthly assurance cycle.
Do data centres in India qualify for infrastructure status?India
Yes, above a size threshold. A Ministry of Finance notification of 11 October 2022 added data centres to the Harmonised Master List of Infrastructure sub-sectors, for facilities with at least 5 MW of IT load. The status mainly eases access to long-term finance. State policies in Tamil Nadu, Uttar Pradesh and Maharashtra add their own land, stamp duty and power terms.
How are data centre construction disputes resolved in the UAE?UAE
Where the contract provides for it, by arbitration. Federal Law No. 6 of 2018 on Arbitration, as amended, governs onshore proceedings, and the Dubai International Arbitration Centre administers cases under its 2022 Rules, having taken over the DIFC-LCIA centre under Dubai Decree No. 34 of 2021. In any forum, a time claim stands or falls on the contemporaneous programme record.
Do data centre providers in Saudi Arabia need to register with a regulator?Saudi Arabia
Yes, if they offer data-centre services to others. Since 1 January 2024, the Communications, Space and Technology Commission's Data Centre Services Regulations have required registration of each facility, including during development, and cloud services carry a separate registration. The building works must also meet the Saudi Building Code 2024, mandatory from 30 June 2025, so approvals belong in the programme from day one.
Where is data centre capacity being built in Oman?Oman
Muscat and Salalah are the main locations. Salalah pairs data-centre space with subsea cable landings on routes between Asia, Africa and Europe. For programme planning, the practical points are grid and cooling connections, the permit the Telecommunications Regulatory Authority has required since 2024 for data-centre and cloud services, and the Personal Data Protection Law issued by Royal Decree 6/2022.