P50 vs P80: how to set a defensible completion date
A single completion date is a fiction. How QSRA turns P50, P80 and P90 into decisions on the working programme, commitment and contingency.
Read
We run risk management as a working control, not a compliance file. Risks are surfaced in facilitated workshops, scored on a 5x5 matrix and owned in a live register. Where the decision warrants it, we model the register against the programme and the estimate to give P50, P80 and P90 positions that a board, funder or bid committee can act on.
Identify. Quantify. Decide.

| Score | Label | Guide |
|---|---|---|
| 1 | Rare | Under 10% |
| 2 | Unlikely | 10% to 30% |
| 3 | Possible | 30% to 50% |
| 4 | Likely | 50% to 70% |
| 5 | Almost certain | Over 70% |
Impact is scored 1 (Negligible) to 5 (Severe) on time, cost and performance, with thresholds calibrated per project to budget, programme float and contractual limits such as delay damages.
Listed companies must describe their risk management policy in the board's report under section 134(3)(n) of the Companies Act, 2013, and the top 1,000 listed entities must run a risk management committee under SEBI LODR Regulation 21. On public and multilateral-funded programmes, environmental assessments and regulatory approvals often sit on the critical path, as they did on the World Bank Tawi River programme, so we model them as risk drivers rather than fixed durations.
PPP projects are regulated emirate by emirate: Abu Dhabi under Law No. 2 of 2019, administered by ADIO, and Dubai under Law No. 22 of 2015. Most contracts use FIDIC forms with heavily amended particular conditions, so the register must follow the risk allocation actually signed, not the standard form. Authority approvals, utility connections and design readiness belong in the model as discrete risk drivers.
PPP and privatisation projects fall under the Private Sector Participation Law (Royal Decree M/63, 2021), with the National Center for Privatization & PPP structuring projects. Under Saudi Arabia's new Government Tenders and Procurement Law, the Article 67 change-order limits of 10% for new items and 20% in total belong in the risk register, and although the maximum delay penalty on works contracts falls to 15%, price adjustment is still limited to the three Article 66 triggers, so material price, tax and unforeseeable physical risks should still be priced and registered explicitly. Each of these laws sets how much variation, delay and funding risk each party carries, so registers and cost models should be checked against the law that governs the contract. See what the new procurement law changes.
Power and water IPPs, including Oman's first utility-scale waste-to-energy project at Barka, are procured by Nama Power and Water Procurement Company under the Sector Law (Royal Decree 78/2004). Other long-term concessions fall under the Public-Private Partnership Law (Royal Decree 52/2019). On the Barka waste-to-energy bid, where tender commitments would set obligations for 25 years, we stress-tested the bid programme against design and permit lead times and reviewed risk allocation against the FIDIC Silver Book.
We treat the risk register as a decision tool, not a compliance record. Every High and Critical risk has an owner, a response and a cost, and the Monte Carlo model is built from the same register, so every number the board sees traces back to a named risk. We bind each percentile to an action: P50 drives the working programme, P80 the commitment and contingency, and the gap between them is held and reported like money.
Bid assurance on a waste-to-energy bid whose tender commitments would bind for 25 years.
Programme assurance where approvals sat on the critical path but were never modelled.
Independent systems assurance across a complex multi-contract programme.
A single completion date is a fiction. How QSRA turns P50, P80 and P90 into decisions on the working programme, commitment and contingency.
ReadStress-test your tender programme before you sign. Independent bid schedule review that exposes optimism, lead-time and FIDIC risk before it becomes a dispute.
ReadWhat the DCMA 14-point schedule assessment checks, why BEI and CPLI matter, and a worked Primavera P6 example of a failing programme.
Read
Send us the programme, the estimate or the current register. We will tell you where the exposure sits and whether a quantitative analysis is worth running. A principal replies within one working day.