Secure the power date. Prove the handover.

A data centre is judged on one date: the day the customer's first hall goes live. That date depends on the grid, on factory slots for long-lead equipment and on five levels of commissioning, and a liquidated damages clause usually sits behind it. From Chennai, Project Assure brings planning, controls, risk, forensic and PMO discipline to data-centre programmes for clients in India, the UAE, Saudi Arabia and Oman.

Power. Commissioning. Handover.

In brief

Data Centres consultancy

Data-centre project assurance is independent planning, controls, risk and delay analysis for the delivery of data centres, from the utility power date through long-lead equipment, MEP installation and L1 to L5 commissioning to phased handover. Project Assure provides it from Chennai for owners, developers, contractors and lenders in India, the UAE, Saudi Arabia and Oman.
Sub-sectors

Where we work in data centres.

Hyperscale campusesMulti-building, multi-phase campuses where the utility connection and phased hall release set the pace. One programme has to hold several buildings, a shared substation and the customer's capacity ramp.
ColocationShell and core built ahead of demand, then fitted out hall by hall as tenants sign. Tenant fit-out dates and staged commissioning need to sit in the same programme as the base build.
EdgeSmaller, repeatable sites delivered in numbers. The risk sits in permits, site power and logistics across many locations, so standard templates and portfolio reporting matter more than one deep schedule.
AI/HPC high-densityHalls built for high rack densities and liquid cooling. Coolant distribution, heavier power infrastructure and newer supply chains add commissioning steps and long-lead items the programme must carry.
Enterprise & sovereignFacilities built for one organisation or for government data. Security, data residency and approval gates add review cycles, and procurement rules shape how changes and delays are handled.
Data Centre Consultancy

Our data centre consultancy service

The integrated master programme, long-lead procurement, L1 to L5 commissioning and handover planning, set out stage by stage.

See the service
Engineer checking a laptop beside glass-fronted server cabinets inside a data hall
Project Assure Data Centre Intelligence

Know the market before you fix the site.

A globe of global data-centre capacity, scored for market risk by data-centre type and geography. Choose a type and a place, and the platform ranks the risks against peer markets, with the evidence or basis behind each rating.

13,293Data-centre sites
89Countries
6facility types risk-rated
  • Hyperscale cloud
  • AI and HPC
  • Wholesale colocation
  • Retail colocation
  • Edge
  • Enterprise and sovereign
  • Open access. No sign-in.

13,293 data centres · 89 countries

Explore 13,293 sites (opens in a new tab)
Services

How each service applies.

  • PlanningIntegrated master programme, speed to power, long-lead equipment and L1 to L5 commissioning.
  • Project controlsRules of credit for MEP and commissioning, earned value and period forecasts.
  • RiskP50 and P80 ready-for-service dates and contingency for power and equipment risk.
  • ForensicDelay damages, extension of time and concurrency on late handovers.
  • DisputesNotices, position papers and delay evidence prepared for counsel and any appointed expert when a handover is contested.
Pressure points

Where these programmes come under pressure.

  • Speed to power
  • Long-lead MEP equipment
  • IST and commissioning
  • Liquidated damages
  • Phased handover
Markets

Where we follow the build-out.

India

  • Mumbai and Navi Mumbai
  • Chennai
  • Hyderabad
  • Noida and NCR

GCC

  • Dubai
  • Abu Dhabi
  • Riyadh
  • Dammam
  • Muscat
  • Salalah
Clients

Who we work with.

  • Owners and developers
  • Contractors
  • Operators
  • Lenders and investors
What we deliver

How our services apply

  • Speed-to-power planningUtility connection, substation and energisation dates logic-linked into the programme, so the power date drives sequencing from day one.
  • Long-lead equipment controlGenerators, UPS, switchgear, chillers and transformers tracked from specification to factory slot, witness test and delivery, tied to site logic.
  • Commissioning and IST programmesL1 to L5 commissioning planned as dated activities with prerequisites and owners, so integrated systems testing is not squeezed at the end.
  • Progress, cost and earned valueRules of credit for MEP and commissioning, with earned value and forecasts that reconcile with the programme each period.
  • Schedule risk on the ready-for-service dateP50 and P80 dates for each data hall, driven by power, equipment and commissioning risk, not a single deterministic finish.
  • Delay damages and EOT analysisDelay damages, extension of time and concurrency tested against the contemporaneous programme record, for owners and contractors alike.
  • Phased handover and hall releaseSectional completion planned hall by hall, with documentation, training and operational readiness tracked to each release.
  • PMO and governance reportingOne reporting rhythm for owner, contractor, operator and lender, with decisions, interfaces and risks owned and dated.

All services

Method

From power to handover: the chain that sets the date

PowerFix the utility connection and energisation dates first. Every later activity depends on them, and they are the dates the project controls least.
EquipmentMap long-lead MEP from design freeze to factory slot, witness test and delivery. A late order shows here months before it shows on site.
InstallationSequence shell, core and data halls for phased release. Agree rules of credit for MEP progress so the forecast stays honest.
CommissioningPlan L1 to L5 with real durations and prerequisites. Integrated systems testing needs permanent power, complete controls and witnesses on site.
HandoverRelease halls in the order customers need them. Tie each release to its sectional date, its delay damages and its readiness evidence.
RecordKeep the contemporaneous record every period: updates, notices, progress and the reasons for change. Any later delay analysis will rest on it.
Standards and practice

The standards we work to

International

  • Uptime Institute Tier Standard: Topology (2018 revision)
  • ANSI/TIA-942-C (May 2024), Telecommunications Infrastructure Standard for Data Centers
  • ANSI/BICSI 002-2024, Data Center Design and Implementation Best Practices
  • ISO/IEC 22237-1:2021, Information technology: Data centre facilities and infrastructures, Part 1: General concepts
  • ANSI/ASHRAE Standard 90.4-2025, Energy Standard for Data Centers
  • ASHRAE Guideline 0-2019, The Commissioning Process
  • FIDIC Conditions of Contract for Plant and Design-Build (Yellow Book), 2nd edition 2017, reprinted 2022 with amendments: Sub-Clause 8.8 (Delay Damages) and Sub-Clause 10.2 (Taking Over Parts)
  • FIDIC Conditions of Contract for EPC/Turnkey Projects (Silver Book), 2nd edition 2017, reprinted 2022 with amendments
  • SCL Delay and Disruption Protocol, 2nd edition (February 2017)
  • AACE International Recommended Practice 29R-03, Forensic Schedule Analysis (2011)
  • ISO 31000:2018, Risk management: Guidelines

India

  • Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023
  • Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022
  • Ministry of Finance (Department of Economic Affairs) notification of 11 October 2022 adding data centres of at least 5 MW IT load to the Harmonised Master List of Infrastructure sub-sectors
  • National Building Construction Standards 2026 (SP 7:2026), Fire and Life Safety. State building bye-laws and fire rules may still refer to the National Building Code 2016 until the state adopts the new standards
  • Digital Personal Data Protection Act, 2023 and Digital Personal Data Protection Rules, 2025 (notified 13 November 2025, phased commencement over 18 months)
  • Indian Contract Act, 1872: sections 55, 73 and 74
  • Arbitration and Conciliation Act, 1996

GCC

  • UAE: Civil Transactions Law, Federal Decree-Law No. 25 of 2025 (in force from 1 June 2026), replacing Federal Law No. 5 of 1985
  • UAE: Federal Law No. 6 of 2018 on Arbitration, as amended by Federal Decree-Law No. 15 of 2023
  • UAE: Federal Decree-Law No. 45 of 2021 on the Protection of Personal Data
  • Saudi Arabia: CST Data Centre Services Regulations (in force from 1 January 2024)
  • Saudi Arabia: Saudi Building Code 2024 (mandatory from 30 June 2025)
  • Saudi Arabia: Civil Transactions Law, Royal Decree No. M/191 (in force from 16 December 2023)
  • Saudi Arabia: Government Tenders and Procurement Law, Royal Decree No. M/128 (2019), in force until the new law takes effect, and still the governing law for works and purchases tendered under it
  • Saudi Arabia: Government Tenders and Procurement Law, Royal Decree No. M/76 dated 27/2/1448H (10 August 2026), published in the Umm Al-Qura Official Gazette on 4 September 2026 and taking effect 120 days after publication (Article 101)
  • Saudi Arabia: Arbitration Law, Royal Decree No. M/34 (2012)
  • Oman: Civil Transactions Law, Royal Decree 29/2013
  • Oman: Personal Data Protection Law, Royal Decree 6/2022
  • Oman: Arbitration Law, Royal Decree 47/97
Regional practice

Data Centres in India and the GCC

India

The path to a ready-for-service date in India often runs through the state distribution utility and the Electrical Inspectorate: under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, installations above the voltage the state has notified for self-certification need the Electrical Inspector's approval before they are energised. At the 33 kV-and-above connections typical of data centres, that approval is usually required. Late completion is usually argued under sections 55 and 74 of the Indian Contract Act, 1872, where the court awards reasonable compensation up to the agreed sum, and loss generally has to be shown unless it is hard to prove. Disputes generally go to arbitration under the Arbitration and Conciliation Act, 1996. Facilities of at least 5 MW IT load have had infrastructure status since the Ministry of Finance notification of 11 October 2022, which often brings lender reporting into the controls cycle.

United Arab Emirates

Capacity clusters around Dubai and Abu Dhabi, and in Dubai the DEWA energisation date usually sets when integrated systems testing can start. Since 1 June 2026, Federal Decree-Law No. 25 of 2025 has replaced the 1985 Civil Transactions Law: liquidated damages remain valid, but a court may reduce an agreed sum shown to be exaggerated or where the employer's own fault contributed to the harm, and contracts signed earlier may still turn on the 1985 law. Contracts are commonly FIDIC-based with bespoke amendments, and where the contract provides for arbitration, disputes go to arbitration under Federal Law No. 6 of 2018 (as amended), often at DIAC or arbitrateAD.

Saudi Arabia

The Communications, Space and Technology Commission's Data Centre Services Regulations, in force since 1 January 2024, require providers of data-centre services to register each facility by its stage of development, with a Qualifying category for data centres still under development. The Saudi Building Code 2024 has been mandatory since 30 June 2025, and Council of Ministers Decision No. 286 of 9 October 2024 made the occupancy certificate a condition of full electrical activation. Under the Civil Transactions Law (Royal Decree M/191), a court may, on the contractor's application, reduce agreed delay compensation that was overestimated or where the obligation was partly performed. Where a government entity tenders the facility without an exemption continued from the 2019 law, such as those for the Public Investment Fund and the Saudi Central Bank, Article 70 of Saudi Arabia's new Government Tenders and Procurement Law caps works delay penalties at 15% of contract value. See what the new procurement law changes.

Oman

Activity centres on Muscat and on Salalah, a landing point for subsea cables between Asia, Africa and Europe. Salalah sits on the Dhofar power system, which has run separately from the northern grid, and the second phase of OETC's Rabt interconnection is planned to join the two, so the connection route and date belong in the programme from the start. Under Article 267 of the Civil Transactions Law (Royal Decree 29/2013), a court may adjust agreed compensation to the actual damage on either party's application, so delay damages need a loss record behind them; private disputes may go to the Oman Commercial Arbitration Centre.

Our approach

How we work in data centres

We treat a data centre as a power and commissioning programme with a building around it. The programme starts from the energisation date and the ready-for-service commitment, works back through integrated testing, MEP installation and long-lead equipment, and keeps each period's record as if a delay analysis may one day depend on it. We do not design facilities and we are independent of contractors and suppliers, so our reports say what the evidence shows.

Other sectors

Related work in other sectors

These cases come from rail and energy programmes, not data centres. They show disciplines a data-centre programme needs: systems assurance, P50 and P80 risk, and forensic windows analysis.

UAE · Rail systems · PMO & governance

Etihad Rail Stage 2 & 3

Independent systems assurance across a complex multi-contract programme.

  • Systems assurance framework established
  • Design stage-gate assessment integrated
  • Assurance deliverables through construction and commissioning
Read the case study
Oman · Energy · Risk management

Barka waste-to-energy IPP

Bid assurance on a waste-to-energy bid whose tender commitments would bind for 25 years.

  • Bid programme stress-tested against design and permit lead times
  • Risk allocation reviewed against FIDIC Silver Book
  • Commercially defensible position established
Oman · Rail · Forensic planning

Hafeet Rail

EOT entitlement and forensic windows analysis on a major rail programme in dispute.

  • Forensic windows analysis produced
  • Design-change impacts separated from concurrent contractor causes
  • EOT entitlement structured and substantiated
Read the case study
Insights

Further reading

FAQ

Data Centres: common questions

What does Project Assure do on data-centre projects?
We plan and assure delivery. That covers the integrated programme from power date to handover, long-lead equipment tracking, L1 to L5 commissioning plans, earned value reporting, P50 and P80 schedule risk, and delay analysis where liquidated damages or extensions of time are in issue. We do not design facilities. Our work tests whether the programme to deliver them is credible.
Why does speed to power drive data-centre schedules?
Because nothing can be tested or handed over without permanent power. The utility connection, substation works and energisation approvals often take longer than the building, and they are the dates the project controls least. We put them in the programme logic from day one, so a slipped grid date shows its effect on integrated systems testing and handover the week it happens.
How do delay damages work when data halls are handed over in phases?
Usually through sections. Under the FIDIC 2017 Yellow Book, Sub-Clause 8.8 sets delay damages per day after each Time for Completion, up to any maximum in the Contract Data, and Sub-Clause 10.2 reduces them in proportion to value when the Employer takes over a Part that is not itself a Section. Particular Conditions often change this, so we map each hall's dates against the signed contract.
Which types of data centre does Project Assure cover?
Six common types: hyperscale campuses, wholesale and retail colocation, edge sites, AI and high-performance computing halls, and enterprise or sovereign facilities. The controls discipline is the same throughout. What changes is where the risk sits: power and phasing on campuses, customer fit-out on colocation, repeatability on edge, cooling and power density on AI, and approval gates on sovereign builds.
Is the Data Centre Intelligence platform free to use?
Yes. Data Centre Intelligence at dc.projectassure.in is open access, with no sign-in. It maps 13,293 data-centre sites across 89 countries on a globe and scores market risk by data-centre type and geography, with the evidence or basis behind each rating. It is built to frame siting and phasing questions before a programme is fixed.
What has to happen before a data centre in India can be energised?India
Under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, installations above the voltage the state has notified for self-certification need the Electrical Inspector's approval before they are energised. At the 33 kV-and-above connections typical of data centres, that approval is usually required. Add the utility's connection works and any green energy open access approvals, and the power path often becomes the critical path.
Are liquidated damages still enforceable in the UAE under the new Civil Transactions Law?UAE
Yes. Federal Decree-Law No. 25 of 2025, in force from 1 June 2026, keeps agreed damages valid. A court may still reduce an amount shown to be exaggerated, or where the employer's own fault contributed to the harm. Contracts signed before then may still turn on the 1985 law. Either way, the contemporaneous programme record decides how a late data-centre handover is treated.
Does a data centre under construction in Saudi Arabia need to be registered?Saudi Arabia
Yes, where it will provide data-centre services. The Communications, Space and Technology Commission's Data Centre Services Regulations, in force since 1 January 2024, register each facility by its stage of development, with a category for data centres under development. Registration does not replace building permits, and full electrical activation depends on the occupancy certificate, so both belong in the programme.
What should a data-centre programme in Oman allow for?Oman
The grid connection first. Salalah sits on the Dhofar power system, which has run separately from the northern grid, and the second phase of OETC's Rabt interconnection is planned to join them. Programmes in Muscat and Salalah should also allow for personal data rules under Royal Decree 6/2022, and for agreed delay damages that an Omani court can adjust to actual loss.

Test the date before you commit to it.

Send us the programme, the contract dates or only the ready-for-service commitment. We will show where power, equipment and commissioning put it at risk, and what the delay damages exposure looks like.