What does Project Assure do on data-centre projects?
We plan and assure delivery. That covers the integrated programme from power date to handover, long-lead equipment tracking, L1 to L5 commissioning plans, earned value reporting, P50 and P80 schedule risk, and delay analysis where liquidated damages or extensions of time are in issue. We do not design facilities. Our work tests whether the programme to deliver them is credible.
Why does speed to power drive data-centre schedules?
Because nothing can be tested or handed over without permanent power. The utility connection, substation works and energisation approvals often take longer than the building, and they are the dates the project controls least. We put them in the programme logic from day one, so a slipped grid date shows its effect on integrated systems testing and handover the week it happens.
How do delay damages work when data halls are handed over in phases?
Usually through sections. Under the FIDIC 2017 Yellow Book, Sub-Clause 8.8 sets delay damages per day after each Time for Completion, up to any maximum in the Contract Data, and Sub-Clause 10.2 reduces them in proportion to value when the Employer takes over a Part that is not itself a Section. Particular Conditions often change this, so we map each hall's dates against the signed contract.
Which types of data centre does Project Assure cover?
Six common types: hyperscale campuses, wholesale and retail colocation, edge sites, AI and high-performance computing halls, and enterprise or sovereign facilities. The controls discipline is the same throughout. What changes is where the risk sits: power and phasing on campuses, customer fit-out on colocation, repeatability on edge, cooling and power density on AI, and approval gates on sovereign builds.
Is the Data Centre Intelligence platform free to use?
Yes. Data Centre Intelligence at dc.projectassure.in is open access, with no sign-in. It maps 13,715 data-centre sites across 135 countries on a globe and scores market risk by data-centre type and geography, with the evidence or basis behind each rating. It is built to frame siting and phasing questions before a programme is fixed.
What has to happen before a data centre in India can be energised?India
Under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, installations above the voltage the state has notified for self-certification need the Electrical Inspector's approval before they are energised. At the 33 kV-and-above connections typical of data centres, that approval is usually required. Add the utility's connection works and any green energy open access approvals, and the power path often becomes the critical path.
Are liquidated damages still enforceable in the UAE under the new Civil Transactions Law?UAE
Yes. Federal Decree-Law No. 25 of 2025, in force from 1 June 2026, keeps agreed damages valid. A court may still reduce an amount shown to be exaggerated, or where the employer's own fault contributed to the harm. Contracts signed before then may still turn on the 1985 law. Either way, the contemporaneous programme record decides how a late data-centre handover is treated.
Does a data centre under construction in Saudi Arabia need to be registered?Saudi Arabia
Yes, where it will provide data-centre services. The Communications, Space and Technology Commission's Data Centre Services Regulations, in force since 1 January 2024, register each facility by its stage of development, with a category for data centres under development. Registration does not replace building permits, and full electrical activation depends on the occupancy certificate, so both belong in the programme.
What should a data-centre programme in Oman allow for?Oman
The grid connection first. Salalah sits on the Dhofar power system, which has run separately from the northern grid, and the second phase of OETC's Rabt interconnection is planned to join them. Programmes in Muscat and Salalah should also allow for personal data rules under Royal Decree 6/2022, and for agreed delay damages that an Omani court can adjust to actual loss.