What does a project planning consultant in Chennai do?
We prepare and control the programme: a logic-linked critical path network showing how, in what order and by when the works will be delivered. For clients across India that covers:
- Tender programmes that win work without committing to dates the bid cannot support.
- Baseline programmes built from the contract, the design and procurement lead times, and the approvals on the path.
- Baseline review and acceptance for owners and funders who need to know whether a contractor's programme is sound before accepting it.
- Progress updating and look-ahead programmes that keep the record honest every period.
- Recovery and mitigation programmes when the project is already behind.
We work in Primavera P6 and Microsoft Project, in the native files your contract specifies. See our project planning service for the full scope.
How do Indian contracts shape the programme?
The programme has to match the contract's own clock. On CPWD works, Clause 5 of the General Conditions of Contract 2023 calls for a Time and Progress Chart within seven working days of award, a progress report by the 5th of each month, and a revised programme once progress falls behind by more than 10% of the stipulated period. NHAI EPC agreements measure performance against the Project Milestones in Schedule J, counted from the Appointed Date, so the baseline must map cleanly to them. Highway projects under the Hybrid Annuity Mode follow the MoRTH Model Concession Agreement, revised in September 2026, while projects awarded earlier run on the November 2020 version. Central sector projects of Rs 150 crore and above also report to MoSPI's PAIMANA monitoring portal.
What does a Primavera P6 schedule audit check?
Whether the network is built well enough to be trusted. We run the DCMA 14-point and GAO schedule checks on the baseline and each update: missing logic, hard constraints, high float, negative float, out-of-sequence progress and a critical path that does not run continuously to completion. Each failure is explained in plain terms with the fix. Our guides to what a Primavera P6 schedule audit finds, the DCMA 14-point assessment and seven red flags in a P6 schedule show what we look for.
How is earned value measured on Indian projects?
From objective progress. Public works pay running account bills against quantities recorded in the measurement book, usually to the relevant part of IS 1200, which gives earned value an objective base when the records are kept properly. We agree rules of credit for each type of work, load the schedule with cost, and report planned value, earned value and actual cost with SPI, CPI and a forecast of final cost and completion each period. On central sector projects the owner-side controls also have to reconcile with what is reported to PAIMANA. See our project controls and EVM service.
When does a project in India need QSRA?
When someone has to commit to a date or a contingency and wants to know how likely it is. Quantitative schedule risk analysis replaces a single completion date with P50, P80 and P90 dates, so the team plans to one and the organisation commits to another. On public and multilateral-funded programmes, environmental assessments and regulatory approvals often sit on the critical path, so we model them as risk drivers rather than fixed durations. Read P50 vs P80 and see our risk management service.
Our references
For the World Bank climate-hazard programme on the Tawi River in Jammu we mapped approval dependencies onto the critical path, rebuilt the baseline to realistic lead times and produced a risk-adjusted P50/P80 programme for funder-grade reporting. Outside India, our forensic windows analysis on Hafeet Rail in Oman set out a substantiated EOT entitlement. When delay has already happened, see our work on forensic delay analysis and dispute avoidance and resolution support.