What does an EOT claim consultant do on an Indian project?
We turn a delay into an entitlement that can be tested, or test one that has been claimed against you. On every matter we work through the same chain:
- Read the contract. The time, extension and notice provisions actually signed, including any special conditions.
- Collect the record. Programmes and updates, progress reports, hindrance registers, notices, correspondence, minutes and site records, with a note of what each can prove.
- Test the programme. Logic, constraints and reported progress are checked before any delay is measured, and every correction is recorded openly.
- Measure the delay. Using a method the records can sustain, separating employer-risk events from contractor-risk causes period by period.
- Set out the entitlement. An EOT application, a claim or a response that an engineer, an arbitral tribunal or a court can follow step by step.
Which contracts govern extension of time in India?
Most Indian public works run on one of a few families of contract, and each has its own clock. On CPWD works, Clause 5 of the General Conditions of Contract 2023 covers time and extension for delay. It calls for a Time and Progress Chart within seven working days of award, a progress report by the 5th of each month, and a revised programme once progress falls behind by more than 10% of the stipulated period, so the programme record it requires is also the record an extension application will rest on. NHAI EPC agreements measure performance against the Project Milestones in Schedule J, counted from the Appointed Date. Highway projects under the Hybrid Annuity Mode follow the MoRTH Model Concession Agreement, revised in September 2026, while projects awarded earlier run on the November 2020 version.
Multilateral-funded and many private projects use FIDIC forms. Under the 1999 Red Book, Sub-Clause 20.1 requires notice within 28 days of awareness and a fully detailed claim within 42 days, with extension of time in Sub-Clause 8.4. Under the 2017 Red Book, Sub-Clauses 20.2.1 and 20.2.4 require a Notice of Claim within 28 days and a fully detailed Claim within 84 days, with extension of time in Sub-Clause 8.5. Special or particular conditions often amend these periods, so we always read the signed contract.
How does Indian law treat late completion and liquidated damages?
Indian construction contracts often treat time as not of the essence, so under section 55 of the Indian Contract Act, 1872 late completion does not make the contract voidable, and the remedy is compensation under sections 73 and 74. Under section 74, courts award reasonable compensation up to the stated liquidated damages, which need not be strictly proved where loss is hard to show. An extension of time therefore matters twice: it moves the date from which damages run, and it frames any claim for prolongation. Concurrent delay is decided largely on the contract and the facts, so we present findings a tribunal can apply under more than one approach. Your counsel advises on the law; we keep our evidence to programme, records and causation.
Where are EOT disputes in India decided?
Contested claims usually go to arbitration under the Arbitration and Conciliation Act, 1996, where section 29A sets time limits for domestic awards, so the delay analysis needs to be ready early. For public procurement, Ministry of Finance guidelines of 3 June 2024 advise against routine arbitration clauses, suggest limiting arbitration to disputes below Rs 10 crore unless approved at senior level, and encourage negotiated settlement and mediation, with a High-Level Committee for high-value matters. The Mediation Act, 2023 promotes mediation, and commercial suits generally need pre-institution mediation under Section 12A of the Commercial Courts Act, 2015.
Clients appoint us in one of two roles, never combined on the same matter: as party-appointed support, building and testing the delay evidence with you and your counsel, or as an independent expert whose duty is to the tribunal. We never act as mediator or arbitrator. See our dispute avoidance and resolution support.
Which delay analysis method suits an Indian claim?
The one the records can sustain, explained in the report, because a tribunal will test the choice. Contemporaneous time impact analysis needs a well-maintained programme and a datable event. Windows and time-slice analysis needs contemporaneous updates with logic maintained through the delay period. Planned against actual comparison suits projects where the updates are unreliable but the as-built record is sound. Our Delay Method Selector, the guide to choosing a delay analysis method and time impact analysis vs windows analysis explain the choice. Before any of them, we run DCMA 14-point and GAO checks on the Primavera P6 baseline and updates; see project planning and controls in India.
When should you bring in an EOT claim consultant?
When the first delay event is identified, not when the claim is rejected. The notices, the hindrance record and the programme updates kept in the first weeks decide what can be proved later, and no analysis can rescue entitlement lost to a missed notice. Our article on when to bring in an EOT claim consultant sets out why timing decides the outcome.
Our references
Our forensic reference is Hafeet Rail, a rail programme in Oman in significant dispute, where our forensic windows analysis separated design-change impacts from concurrent contractor causes and set out a substantiated EOT entitlement. In India, for the World Bank climate-hazard programme on the Tawi River in Jammu we mapped approval dependencies onto the critical path and produced a risk-adjusted P50/P80 programme for funder-grade reporting. Read more about Project Assure in India and our forensic planning and delay analysis service.