Chennai HQ · serving India, UAE, Saudi Arabia and Omaninfo@projectassure.inCall us 24/7 +91 94895 88922
Project Assure
Abu Dhabi Corniche skyline of modern towers across calm Gulf water at dusk
Project Assure in UAE

QSRA and schedule risk analysis consultants in the UAE

We run quantitative schedule risk analysis for owners, lenders, delivery partners and bidders in Dubai, Abu Dhabi and across the Emirates, so the completion date and contingency a board commits to rest on the programme, the register and the contract actually signed.

In short

A quantitative schedule risk analysis (QSRA) runs the logic-linked programme, its duration uncertainty and its discrete risk events through a Monte Carlo simulation thousands of times, giving the probability of finishing by any date. The result is a P50 working date, a P80 commitment and a P90 stress case, and the gap between P50 and P80 is held as an owned contingency. On UAE projects Project Assure checks the Primavera P6 schedule first, maps each risk to the FIDIC clause that allocates it, and models authority approvals, utility connections and design readiness as risk drivers, following AACE RP 57R-09 and ISO 31000.

What is a QSRA, and when is one worth doing on a UAE project?

A QSRA measures how likely the programme is to finish by a given date once uncertainty and risk events are taken into account. It is worth doing when a date or a contingency figure is about to be committed:

  • At bid, before you sign a FIDIC EPC or design-and-build contract, so the tender does not promise what the risk profile cannot support.
  • At sanction or financial close, when a board, funder or lender needs a probabilistic position rather than a single date.
  • At baseline, so the working programme and the contractual commitment are set at stated confidence levels.
  • Before a major re-plan, to test whether a recovery programme is achievable or only hopeful.

See our risk management and QSRA service for the full scope, including quantitative cost risk analysis (QCRA).

How is the programme checked before it is modelled?

Monte Carlo on a schedule with missing logic or hard constraints produces confident nonsense, so we check the Primavera P6 programme before we model it. We run DCMA 14-point and GAO checks, fix open ends and unjustified constraints openly, and record every correction so the model can be reviewed. Our notes on the DCMA 14-point assessment and fixing missing logic in P6 show what those checks look for.

Which UAE risks belong in the schedule risk model?

The ones that actually move completion, modelled as discrete events with a probability and an impact range rather than as wider durations alone. On UAE projects that usually means:

  • Authority approvals and permits, with their real lead times rather than the durations in the tender programme.
  • Utility connections, which often sit on the critical path to commissioning.
  • Design readiness, because that is where most programme slippage starts.
  • Interfaces between packages, systems and operators, especially on rail, aviation and mixed-use programmes.

Correlation is applied between related activities. Without it, good and bad outcomes cancel out and the P80 date looks closer to P50 than it really is.

How should the risk register follow a UAE construction contract?

It should follow the signed risk allocation, not the standard form. Most UAE works contracts use the FIDIC 1999 or 2017 Red, Yellow or Silver Books with heavily amended particular conditions that move ground, approval or design risk between the parties. We map each register entry to the clause that allocates it, so the model shows which risks you carry and which you can price, transfer or claim against. PPP projects are regulated emirate by emirate: Abu Dhabi under Law No. 2 of 2019, administered by ADIO, and Dubai under Law No. 22 of 2015, so concession risk allocation is read from the project agreement made under the law that applies.

How do you choose between P50, P80 and P90?

By the decision, not by habit. P50 is a fair working target with an even chance of being beaten. P80 suits contractual commitments and contingency, because it covers most adverse outcomes. P90 is a stress case that lenders and boards use to test funding headroom. We bind each percentile to an action and agree drawdown rules for the contingency between P50 and P80, so it is spent against named risks and not absorbed as general float. Read more in P50 vs P80: which completion date to commit to.

Our references

On the World Bank climate-hazard programme on the Tawi River in India we rebuilt the baseline to realistic lead times and produced a risk-adjusted P50/P80 programme for funder-grade reporting. On the Barka waste-to-energy bid in Oman we stress-tested the bid programme against design and permit lead times and reviewed risk allocation against the FIDIC Silver Book. On Etihad Rail Stage 2 and 3 in the UAE we provided independent systems assurance across construction and commissioning. When delay has already happened, see our forensic delay analysis and EOT claim consultant pages for the UAE, and read more about Project Assure in the UAE.

FAQ

QSRA and schedule risk analysis, UAE: common questions

Do you provide QSRA and schedule risk analysis in the UAE?
Yes. We run quantitative schedule risk analysis and quantitative cost risk analysis for owners, lenders, delivery partners and bidders in Dubai, Abu Dhabi and across the Emirates, from the risk workshop and register to the Monte Carlo model and the board report.
What do you need to start a QSRA?
A logic-linked programme, ideally the native Primavera P6 file, the current risk register and the contract. We check the schedule first, because a Monte Carlo model on a programme with missing logic or hard constraints gives misleading dates.
Which standards do you follow for schedule risk analysis?
AACE International RP 57R-09 for integrated cost and schedule risk analysis using risk drivers and Monte Carlo simulation of a CPM model, AACE RP 40R-08 for contingency, ISO 31000:2018 and IEC 31010:2019.
Is a P80 date the same as the contract completion date?
Not necessarily. P80 is a confidence level from the model. Many owners and contractors commit to a P80 date, but the contract date is whatever was signed, so we report the probability of meeting it and the contingency needed to protect it.
Can you stress-test a tender programme before we bid in the UAE?
Yes. We test programme commitments, risk allocation and lead times for approvals, design and utilities before submission, so the bid date and price reflect the risk you will carry under the amended FIDIC conditions.
Chennai city skyline at dusk under a vivid pink and violet sky

A date or a contingency to commit in the UAE?

Send us the programme, the register and the contract. A principal will tell you whether a quantitative analysis is worth running before any work is priced.