Primavera P6 constraints explained: hard vs soft constraints and when to avoid them

Constraints let you impose dates on a P6 schedule. Used in place of logic, they distort float, hide the critical path and fail the DCMA hard constraints check.

In short

Primavera P6 constraints impose dates that override or cap the dates logic would calculate. Soft constraints such as Start On or After still let logic move the activity later, while hard constraints such as Finish On or Before, Start On, Finish On and the Mandatory types fix or cap dates, and Mandatory constraints can override logic altogether. The DCMA 14-point assessment expects hard constraints on fewer than 5% of incomplete activities, and each one should be justified by a contract or external date.

Constraints in Primavera P6 are imposed dates that limit when an activity can start or finish, overriding or capping the dates the scheduling engine would otherwise calculate from logic and calendars. They are sometimes necessary, for contract milestones or genuine external dates, but used in place of logic they distort float, hide the true critical path and fail the DCMA hard constraints check.

This guide explains each P6 constraint type, the difference between hard and soft constraints, how mandatory constraints behave, and how to audit constraints in a live schedule.

What are the constraint types in Primavera P6?

Each activity can carry a primary constraint and, for some combinations, a secondary constraint. The table shows what each one does.

P6 constraintWhat it doesAffectsDCMA class
Start On or AfterThe activity cannot start before the date. Logic can still push it later.Early startSoft
Finish On or AfterThe activity cannot finish before the date.Early finishSoft
Start On or BeforeCaps the late start. If logic cannot meet it, negative float appears.Late startHard
Finish On or BeforeCaps the late finish (a deadline). It does not move the early dates.Late finishHard
Start OnSets both early and late start to the date. Predecessors can still push it later, which produces negative float.Early and late startHard
Finish OnSets both early and late finish to the date, with the same behaviour as Start On.Early and late finishHard
Mandatory StartFixes the start date regardless of logic. Can schedule the activity in breach of its predecessors.Early and late startHard
Mandatory FinishFixes the finish date regardless of logic.Early and late finishHard
As Late As PossibleSchedules the activity as late as it can go without delaying its successors, using up its free float.Early datesSoft

The DCMA guidance was written in Microsoft Project terms (Must Start On, Must Finish On, Start No Later Than, Finish No Later Than as hard). The P6 mapping above is the one reviewers commonly apply. Agree the mapping with the reviewing party before a formal assessment, because some reviewers treat Start On and Finish On differently.

What is the difference between hard and soft constraints in P6?

A soft constraint sets an earliest date but still lets logic move the activity later. Start On or After and Finish On or After are soft: if a predecessor slips, the activity moves with it and float behaves normally.

A hard constraint fixes a date or caps the late dates, so the schedule cannot respond freely to delay. It either produces negative float when logic cannot meet the date (Start On or Before, Finish On or Before, Start On, Finish On) or overrides the logic altogether (Mandatory Start, Mandatory Finish). Hard constraints are what the DCMA check counts.

What does a Mandatory Start constraint do?

A Mandatory Start constraint sets the activity's early and late start to the constraint date, whatever its predecessors say. If a predecessor finishes later than that date, P6 still starts the activity on the imposed date, so the schedule shows work starting before the work it depends on is complete. The backward pass also takes the imposed date, so predecessors that cannot meet it show negative float. Mandatory Finish behaves the same way on the finish date.

This is why mandatory constraints are the most damaging type. They can make a schedule look as if it meets its dates when the logic says it cannot, and the logic breach appears only in the schedule log or a logic check.

How do constraints distort float and the critical path?

A constraint changes the early dates, the late dates or both, so it changes total float:

  • Late-date constraints (Finish On or Before, Start On or Before) shorten the backward pass. If logic cannot meet the date, the constrained activity and its predecessors show negative float. See total float and negative float explained.
  • Start On or After can delay an activity's early dates and use up float downstream. On its own it does not create negative float.
  • Start On, Finish On and Mandatory constraints pin the activity's late dates, so it tends to show zero or negative float even if the logic has room. A path can look critical because of the constraint rather than the work.
  • Mandatory constraints also break the chain of logic: delays upstream do not flow through to successors, so the real driving path can be hidden behind the constrained activity.

In a logic-driven schedule, the critical path is the longest path to project completion, which P6 can display directly using the longest path option. Total float of zero or less is a common proxy, but constraints, multiple calendars and negative float can make the two differ. When constraints are present, check the longest path rather than relying on float alone.

Why does the DCMA 14-point assessment penalise hard constraints?

Check 5 of the DCMA 14-point assessment counts incomplete activities with hard constraints. The threshold is fewer than 5% of incomplete activities. Soft constraints are not counted. Hard constraints are treated as high risk because they stop the schedule from responding to delay, so the forecast dates no longer come from the logic.

The GAO Schedule Assessment Guide gives similar advice: hard constraints should be used only for genuinely fixed dates and each one should be justified. Many owners' specifications go further and restrict constraints to named contract milestones.

Constraints also weaken forensic delay analysis. Where a baseline or update carries hard constraints, it becomes hard to show whether a forecast date moved because of the work or because a constraint held it in place. Before a delay analysis relies on a schedule, its constraints need to be identified and their effect tested.

When is a constraint justified, and when should you use logic instead?

Justified uses of constraints

  • Contract milestones: a Finish On or Before on a completion or sectional completion milestone where the date is fixed in the contract. It shows negative float when the programme is behind, which is the warning you want.
  • External dependencies: a Start On or After on an activity that cannot begin before a known external date, such as a permit, an access date or a utility connection date outside the contractor's control.
  • Seasonal windows: a Start On or After for offshore, marine or winter-restricted work where the window is fixed.

When to use logic instead

  • Internal dependencies: if a task waits for other work in the project, link it with a relationship (with a justified lag if needed) rather than constraining it to a date.
  • Resource limits: do not use date constraints to imitate resource availability. Use resource assignments, resource calendars and levelling.
  • Contingency: do not hold schedule contingency with a constraint. Show it as a clearly labelled contingency activity on the path to the completion milestone.

A good rule: if the date is not imposed from outside the project and is not negotiable, model it with logic. This keeps the schedule responsive to change.

How do you audit constraints in a P6 schedule?

  1. Add the Primary Constraint, Primary Constraint Date, Secondary Constraint and Secondary Constraint Date columns to the Activities view.
  2. Filter for incomplete activities where Primary Constraint is not empty, and group by constraint type.
  3. Count the hard constraints against all incomplete activities. Fewer than 5% passes the DCMA check.
  4. For each constraint, compare the constraint date with the calculated early dates and total float. A large gap or negative float shows where logic and constraint disagree.
  5. Reschedule (F9) and open the schedule log, which lists constrained activities and activities scheduled out of logic sequence.
  6. Check each remaining constraint has a recorded reason, such as a contract clause or an external date, in a notebook topic or a user-defined field.

A schedule-checking tool or a standard P6 report can list constrained activities in bulk. As part of a project planning review, an independent reviewer such as Project Assure tests each constraint against its justification as well as counting it.

What are the best practices for managing P6 constraints?

  • Keep hard constraints to fewer than 5% of incomplete activities (the DCMA threshold), and fewer still in practice.
  • Record the justification for every constraint in the activity's notes or a user-defined field.
  • Review constraints at every update and remove those that are no longer needed.
  • Use Finish On or Before rather than Mandatory Finish on contract milestones, so negative float shows the slippage instead of hiding it.
  • Avoid Mandatory Start and Mandatory Finish. Do not use them on working activities.
  • Do not use constraints to model internal sequence, resources or contingency.

Constraints used sparingly, justified and reviewed, leave the logic in charge of the dates. That gives a schedule that passes DCMA review and holds up in delay analysis.

FAQ

Common questions

What is the most common Primavera P6 constraint type?
Start On or After is the most common. It models external dependencies such as permit, access or weather-window dates, and as a soft constraint it is not counted in the DCMA hard constraints check.
What is the difference between hard and soft constraints in P6?
A soft constraint, such as Start On or After or Finish On or After, sets an earliest date but still lets logic move the activity later. A hard constraint, such as Finish On or Before, Start On, Finish On, Mandatory Start or Mandatory Finish, fixes or caps a date so the schedule cannot respond freely to delay.
How do Mandatory constraints affect the critical path?
Mandatory Start and Mandatory Finish fix an activity's dates regardless of logic, so upstream delay does not flow through to its successors and the activity can be scheduled before its predecessors finish. This can hide the true driving path and make the schedule unreliable for delay analysis.
Why does DCMA penalise hard constraints?
Hard constraints stop the schedule from responding to delay, so forecast dates no longer come from the logic. The DCMA 14-point assessment fails a schedule where more than 5% of incomplete activities carry hard constraints.
How can I check if my schedule has too many constraints?
Add the Primary and Secondary Constraint columns in P6, filter incomplete activities that carry a constraint, and count the hard ones against all incomplete activities. A schedule-checking tool or a standard P6 report can produce the same list, and each remaining constraint should have a recorded justification.